U.S. Data-Center Developers Announce Plans for More Than 100 Natural-Gas Plants

AI hardware & infrastructure🇺🇸Energy

U.S. data-center developers have announced plans for more than 100 natural-gas plants that supply data centers directly and total over 115 gigawatts, a fast-growing response to long grid-connection delays that could increase emissions and extend reliance on fossil fuels.

Cleanview data cited by MIT Technology Review puts the planned capacity at more than twice California’s peak electricity demand. Most announcements were made since early 2025. The plans do not show how much capacity will ultimately be built.

At the time of the tally, just 4.9 gigawatts of these projects were operating, while 15.8 gigawatts were under construction. Developers are pursuing on-site power because connecting large new facilities can take years, and in some cases up to a decade. Companies racing to expand AI computing can benefit from bringing a data center online sooner.

“Behind the meter” means a plant supplies a facility directly instead of sending electricity through a utility connection. Some projects may later connect to the grid. BloombergNEF estimates that the proposed U.S. plants could emit about 345 million metric tons of carbon-dioxide equivalent a year by 2035 if they are all built and run under its assumptions.

That would be 152 million tons more than supplying the same data centers with average U.S. grid electricity. The total remains uncertain. Analysts warn that plants described as temporary ways to bridge the wait for grid connections could keep running after those connections arrive.

Greater gas demand could also put pressure on fuel prices. Approaches raised in the reporting include faster grid connections, cleaner electricity, and combining gas power with renewable energy or storage.